摘要:传统的无线网络站点搬迁,需要中断现网服务,而且只能串行逐片割接,组织工作复杂,资源投入巨大,因此亟需探讨一种低风险、快速建网的搬迁割接方案。中兴通讯股份有限公司的ZTE BBU+RRU 基站由于采用分布式结构,结合宽带码分多址(WCDMA)同频组网特性,可以方便地实现软搬迁软割接。该方案采用叠加建网然后一次性割接的方法,不影响现网运行,并可以及时回退,能极大地简化搬迁割接工作,降低网络风险。
Abstract:Traditionally, when a radio network site is moved, it is necessary to interrupt existing services and perform a step-by-step serial cutover, which involves complex arrangements and huge resource investments. Therefore, there is an urgent need to discuss a low-risk and fast solution to site moving and cutover. ZTE Base Band Unit and Remote Radio Unit (BBU+RRU) Base Station adopts distributed structure and combines full frequency reuse of the WCDMA system to implement soft site moving and cutover conveniently. The solution is to build an overlay network and make a one-time cutover without any impact on the running of the existing network. Moreover, it supports timely fallback, and can considerably simplify the site moving and cutover operation and lower the network risk.
宽带码分多址(WCDMA)移动通信系统的搬迁割接有多种方案,目前已从传统无线网络的硬搬迁硬割接方案发展到新型的软搬迁软割接方案。对各方案的应用场景、技术原理、可行性分析和实施流程进行深入分析,可为工程实施提供理论和操作依据。
1 传统搬迁割接方案的困境
1.1 搬迁割接的市场需求
随着全世界范围内WCDMA网络第一波建设浪潮的结束,最早投入建设的部分运营网络,逐渐暴露出系统架构缺陷的问题,需要更新换代以支持高速分组接入(HSPA)。如何更好地在原有网络不受影响的情况下,实现搬迁割接,成为运营商关注的一个重要问题。
1.2 传统的搬迁割接流程
传统的搬迁割接,是按照覆盖情况将整个网络分片,选择话务量较低的时间,如夜间,进行搬迁。采用搬迁一片,优化一片的方法进行,逐步完成整个网络的搬迁割接工作。
传统的站点搬迁流程通常如图1所示。
传统的搬迁割接,可以简单地称为“硬搬迁硬割接”。
传统的搬迁割接流程有以下几个弊端:
搬迁当晚必然造成站点业务中断。对机房空间不够大的站点,串行工作引起的业务中断时间更长。